Update On Eastside Gold Project Drill Program

 

VANCOUVER, BC - Columbus Gold Corporation reported an update on the current drill program at its 100% owned Eastside gold project in Nevada. The current drill program consists of 250 rotary holes, of which 175 holes totaling about 45,000 meters (150,000 feet) are planned to be completed in 2015.

During 2015, Columbus to date has drilled 18 holes totaling 3,773 meters (12,378 feet) on the Original Target at the Eastside Gold Project. In addition, and in preparation for the extensive drill program, 6.4-kilometer (4.0 miles) of the road building is now completed from the total planned of 18.4-kilometer (11.5 miles).